Commercial Headquarters Fit-Out

Space purpose & constraints.
The client required high-performance ergonomic task seating, meeting room suites, and agile collaborative zones for a 45,000 sq. ft. headquarters expansion.
Operational hurdles on site.
A strict phased move-in schedule where the 4th floor had to become operational while the 5th floor was still undergoing mechanical commissioning.
- •Coordinating elevator access during restricted commercial tower hours
- •Ensuring identical fabric dye-lots and finish tolerances across multiple procurement batches
- •Rigorous ergonomic chair mechanism testing to avoid day-one warranty complaints
Specification, delivery & assembly.
Dreamz specified heavy-duty synchronized task chairs, modular conference tables with concealed cable channels, and breakout furniture staged in two precise deliveries.
- ✓Conducted ergonomic sampling session with client leadership prior to procurement sign-off
- ✓Staged phased vertical transport after 8 PM to prevent building freight bottlenecks
- ✓Dispatched dedicated Dreamz assembly team to assemble, inspect, and position every unit
Floor handover & verification.
Handover completed on schedule with complete floor readiness and zero disruption to the active 4th-floor workforce.
- •450 chairs and desks inspected and signed off by the facilities lead
- •Full documentation packet and 1-year warranty coverage initiated upon handover
Covered under Dreamz 1-year warranty. Water and fire damage are not covered.